Impact of The Flexim Solution
A timely solution helped protect a project with $4,500,000 in value at stake.
for an exotic-metals Coriolis meter, creating schedule risk for an operation where timing matters.
which delays could quickly impact continuity of operations.
In an HCL offload operation, safety and measurement go hand in hand. The customer required an automatic offload system for HCL to support worker safety, and measurement was critical to the success of the offload process.
The project faced a major constraint: long lead time for an exotic-metals Coriolis meter, creating schedule risk for an operation where timing matters. The urgency was amplified by operational reality. The customer needed HCL for processing and only had an on-site three-day supply, which delays could quickly impact continuity of operations.